WA071: Ray & Recker Direct Well System

Print
Press Enter to show all options, press Tab go to next option

CURRENT PHASE: Construction

Anticipated construction completion: August 2018

Project Description:

Gilbert has contracted with Felix Construction Company to construct a new well site at the northeast corner of Ray and Recker Roads.  Construction is anticipated to begin December 2017 and complete in August 2018.

Construction Phase 1:
Construction work during this phase will begin in December 2017 and complete in January 2018.  Work will be confined to the existing well site on the NE corner of Ray and Recker Roads.  Construction crews will work during daytime hours to perform light construction tasks including placing concrete and some welding activities.  No traffic restrictions are anticipated.

Construction Phase 2:
Construction work during this phase will begin in February 2018 and complete in August 2018. Work will primarily take place within the well site on the NE corner of Ray and Recker Roads as the existing well equipment is removed and a new well facility is constructed.  As construction of the well site progresses, it will be necessary to restrict traffic along Ray Road to install a new section of water line and make a connection to the existing distribution system. 

Thank you in advance for your patience as we make these infrastructure improvements.

Please contact the project hotline at (480) 898-4090 with any questions or concerns regarding this project.